St. Jude’s campus overhaul gets a conditional yes from council

The city register records Nov. 17 approval for the Glenridge Drive church-and-school plan. Exact adopted conditions have not yet been verified.

St. Jude the Apostle Catholic Church and School’s campus overhaul at 7171 Glenridge Drive has won City Council approval with conditions, according to Sandy Springs’ land-use register. The register records the council action for Nov. 17, 2026.⁠[1][2]

The register does not spell out the conditions. The detailed rules discussed below were proposed in the council packet; they have not been verified as the final terms council adopted.⁠[1][2]

The submitted six-phase plan includes a new two-story parish life center, church renovation and expansion, preschool relocation, school administrative improvements, a two-story gymnatorium and a replacement middle-school building.⁠[2]

The proposed conditions kept enrollment limits unchanged: 525 private-school students and 50 day-care children, along with 700 fixed seats in the church’s largest assembly area. They also set a maximum lot coverage of 49% across all phases, subject to verification of impervious-surface calculations and stormwater compliance during permitting.⁠[2]

Our pre-vote traffic report detailed the Spalding Drive turn-lane question. In the council materials, the city transportation engineer directs the applicant to show a right-turn lane at the Spalding entrance. Consultant Kimley-Horn also found a lane warranted, but warned that cost and the roadway’s character could make construction impractical.⁠[2][3]

The proposed ordinance left the number, location and alignment of Spalding driveways subject to the city engineer’s approval. It also allowed a Glenridge Drive turning lane to be required during Phase 2 if the engineer determined one was needed. The register’s approval entry does not establish a final road design.⁠[1][2]

Before the vote, the applicants anticipated moving forward with the first two phases in 2027 or 2028 if approved. Those phases cover playground relocation and the parish-life-center and church work; later phases had no definite timetable in the staff report.⁠[2]

Sources

3 official sources cited in this report. The bracketed numbers in the text link here.