The city says it canceled the original bid and revised the documents. A construction-contract award remains the next step.
Sandy Springs, Georgia, is rebidding its Windsor Parkway sidewalk gap-fill project after canceling the original bid and revising the bidding documents, according to the city’s Nov. 20 capital-project report.[1]
That changes the picture from the Oct. 23 update, which said construction bids received Oct. 6 were under review. The latest report says rebidding is underway and still lists awarding a construction contract as the next step. It does not explain the cancellation, identify the revisions or give a new bidding deadline or construction-start date.[1][2]
The city’s financial statement through September lists a $1.725 million budget for the project, numbered S2161, with $308,692 in cumulative expenditures. Those are project-account figures—not a price for the revised construction contract.[3]
The project had already advanced through an easement agreement: the city’s May 5 council meeting recap says council approved a purchase and sale agreement for driveway and temporary construction easements at 425 Windsor Parkway to support the sidewalk work.[4]