St. Jude’s traffic review points to a Spalding Drive turn lane

The campus overhaul would keep enrollment caps unchanged. Ahead of the Nov. 17 council hearing, a consultant and city engineer agree a right-turn lane is warranted—but construction is not settled.

St. Jude’s proposed campus overhaul would keep its student and church seating limits unchanged. But changes to how drivers enter and leave bring a concrete road question: a traffic consultant and Sandy Springs’ transportation engineer both say a right-turn lane is warranted at the Spalding Drive entrance.⁠[1][2]

City Council is scheduled to hear the request Nov. 17 for St. Jude the Apostle Catholic Church and School at 7171 Glenridge Drive. Conditional-use case U-26-5 would amend the campus’s existing permit. Draft conditions retain limits of 525 private-school students, 50 day-care children and 700 fixed seats in the church’s largest assembly area.⁠[1]

We previously reported the project’s conditional Planning Commission backing. The council staff report confirms that commissioners recommended approval with conditions on Oct. 21; staff also recommends conditional approval. Neither recommendation is final council approval.⁠[1]

A July 30 Kimley-Horn traffic memorandum describes a proposal to reduce four driveways to three: two on Glenridge Drive and one on Spalding. The Spalding driveway would accommodate both entering and exiting traffic, replacing separate entrance-only and exit-only access points there.⁠[2]

The consultant found that a Spalding right-turn lane met the city’s daily and peak-hour criteria, but cautioned that cost and the roadway’s character might make construction impractical. It recommended further coordination with the city. It did not recommend a left-turn lane, citing mixed results under the city’s criteria, roadway impacts and right-of-way constraints.⁠[2]

City review comments in the council packet call for analysis based on observed traffic patterns rather than assumptions about school drop-offs, along with weekend traffic counts. The transportation engineer separately directs the applicant to show a right-turn lane at the Spalding entrance.⁠[1]

Those findings are not a final road design. The draft ordinance leaves the number, location and alignment of Spalding driveways subject to the city engineer’s approval. It also allows a Glenridge turning lane to be required during Phase 2 if the engineer determines one is needed. The site plan remains conceptual and must meet the Development Code.⁠[1]

The broader campus plan includes a parish life center, church renovation and expansion, preschool relocation, a gymnatorium and a replacement middle-school building. The applicants anticipate the first two phases in 2027 or 2028 if approved; later phases have no definite timetable.⁠[1]

The Nov. 17 regular council meeting follows the work session in the Studio Theatre at Sandy Springs City Hall, 1 Galambos Way.⁠[1]

Sources

3 official sources cited in this report. The bracketed numbers in the text link here.

Reporting history