Roswell Road transit-access project completes Phase 1 land acquisition
Utility coordination and permitting remain ahead of Phase 1 bidding. The September report lists 17 of 26 required land acquisitions completed across the project.
Right-of-way acquisition was complete for Phase 1 of Sandy Springs’ Roswell Road transit-access streetscape project, according to the city’s Sept. 18, 2026, capital-project report. Project T0019 would add pedestrian infrastructure, landscaping and lighting to complement transit service.[1]
Acquisition for Phases 2 and 3 remained underway. The report says 17 of 26 required land acquisitions had been completed. It lists final utility coordination, construction-plan permitting and advertising Phase 1 for construction bids as next steps.[1]
The overall project is described as extending along Roswell Road’s east side from the city limit to I-285 and along the west side from the city limit to Long Island. The report records land-acquisition and preparation milestones, not an awarded Phase 1 construction contract.[1]
Sources
1 official source cited in this report. The bracketed numbers in the text link here.
Reporting history
Newest first. Articles reflect what was known at publication.
Proposed Roswell Road land deal puts a 2029 limit on construction access
Published after this articleSandy Springs approves $182,000 deal for county land along Roswell Road
Published after this article