Recommendations
Mount Vernon path budget proposal would shift $700,000 to cover construction quantities
The proposed ordinance lists a $13.23 million construction contract. Staff attributes the largest paving overrun to a bid-quantity error, not work departing from the approved design.
Explore the source documentsA proposed ordinance for Sandy Springs' Oct. 6 council meeting would transfer $700,000 from uncommitted TSPLOST-2016 funds to the Mount Vernon Highway Multi-Use Path and Intersection Improvements Project. It also lists an updated construction contract of $13,230,150.53.
Sources01p. 201p. 4001p. 4501p. 1Staff says the largest paving cost increase arose from the engineer's asphalt-leveling quantity estimate differing significantly from the amount required by the design. A third-party survey found the contractor built the roadway section according to the approved plans.
Sources01p. 41A companion recommendation would retroactively extend Excellere Construction LLC's contract period through Sept. 18 while preserving 25 days of assessed liquidated damages. The city issued a substantial-completion notice Aug. 28 and required punch-list work by Sept. 18; this is not evidence that every remaining item was completed.
Sources01p. 201p. 3601p. 3701p. 39The documents contain inconsistencies requiring clarification: the budget memo's recommendation lists $712,922.13, while the proposed ordinance specifies a $700,000 transfer. The time-extension memo gives both 104 and 109 additional days, while the proposed resolution specifies June 1 through Sept. 18.
Sources01p. 4001p. 4501p. 3601p. 3701p. 39