Mount Vernon–Johnson Ferry final paving depends on underground utility relocations

Two-way traffic was operating on both roads. The September report says Roswell Road signals remained in a temporary configuration pending overhead utility relocation.

Explore the source documents

Final paving for Sandy Springs’ Mount Vernon Highway at Johnson Ferry Road improvements depended on relocating overhead utilities underground, according to the city’s Sept. 18, 2026, capital-project report. Project TS191 still had Georgia Power installations underway, with Comcast and AT&T work to follow.

Sources01

Two-way traffic operations had been implemented on Johnson Ferry Road and Mount Vernon Highway. The report dates the Mount Vernon change to June 4, 2026. Signal installations on Roswell Road were complete in a temporary configuration pending completion of overhead utility relocation.

Sources01

The report also lists remaining curb, gutter and sidewalk work, along with contractor punch-list work. These are September construction milestones, not a final-completion notice.

Sources01