Long Island’s signal could cost Mount Vernon drivers about 40 seconds at evening rush

The consultant modeled less morning network delay but more at evening rush. The intersection project has a year-end construction target—not a confirmed signal-opening date.

Making turns easier at Long Island Drive and Mount Vernon Highway would not make every trip faster. A consultant’s model for the Sandy Springs, Georgia, signal project shows roughly 40 extra seconds for Mount Vernon drivers in either direction during evening rush.⁠[1]

Kimley-Horn’s Feb. 19, 2025, traffic analysis compares signalized and no-build conditions along Mount Vernon—from approximately 1,100 feet west of Long Island Drive to 1,400 feet east of Hammond Drive. In the evening peak, modeled eastbound travel time rises from about 73 seconds to 111 seconds; westbound travel rises from about 52 seconds to 93 seconds.⁠[1]

The morning picture is different. Modeled eastbound travel time falls from about 138 seconds to 117 seconds. Across the analyzed network, total delay falls 12.6% in the morning peak and rises 11.5% in the evening peak. The consultant calls overall network delays “modest.”⁠[1]

Those are modeled scenarios, not measurements from an operating new signal. The memo draws on data from a study completed in 2022 and does not identify the forecast year used in its tables.⁠[1]

The city’s case for the signal centers on safety and turning access. Its project description says vehicles queued in Long Island’s two approach lanes obstruct drivers’ sightlines, while the offset Arlington Cemetery driveway conflicts with left-turn movements on Mount Vernon. The project widens the roadway, realigns the cemetery driveway and adds sidewalks, striping and signs.⁠[2]

The congestion concern surfaced during the earlier design process. One submitted comment acknowledged poor visibility but questioned adding another light near the Hammond Drive signal. The city’s written response says the signals will be coordinated and describes the added through-traffic delay as minimal compared with the expected safety benefits.⁠[3]

The city’s capital-project entry labeled for Nov. 20 still lists the job in construction, with signal mast-arm foundations complete and grading and paving upcoming. Its project webpage targets substantial completion by the end of December 2026 and final closeout in early January 2027. Those are targets, not a confirmed signal-activation date. The city warns of periodic construction delays, with lane closures and flaggers as needed.⁠[2][4]