Hammond Drive widening finishes design and land acquisition; bid preparation underway

The four-lane proposal includes bicycle, pedestrian and transit infrastructure. The September report still describes funding as engineering and right-of-way only.

Final design and right-of-way acquisition were complete for Sandy Springs’ Hammond Drive widening proposal, according to the city’s Sept. 18, 2026, capital-project report. Project S2193 would widen the road to four lanes between Roswell Road and Glenridge Drive and add bicycle, pedestrian and transit infrastructure.⁠[1]

The report lists permits received from the Army Corps of Engineers and Georgia EPD, along with a land-disturbance permit. A construction bid package was under review; advertising for bids and beginning advance utility relocations were listed as next steps.⁠[1]

The project description limits current funding to “PE and ROW only”—engineering and right-of-way work. The entry therefore establishes preparation for construction bidding, not full construction funding or an awarded construction contract.⁠[1]