Hammond Drive widening finishes design and land acquisition; bid preparation underway

The four-lane proposal includes bicycle, pedestrian and transit infrastructure. The September report still describes funding as engineering and right-of-way only.

Explore the source documents

Final design and right-of-way acquisition were complete for Sandy Springs’ Hammond Drive widening proposal, according to the city’s Sept. 18, 2026, capital-project report. Project S2193 would widen the road to four lanes between Roswell Road and Glenridge Drive and add bicycle, pedestrian and transit infrastructure.

Sources01

The report lists permits received from the Army Corps of Engineers and Georgia EPD, along with a land-disturbance permit. A construction bid package was under review; advertising for bids and beginning advance utility relocations were listed as next steps.

Sources01

The project description limits current funding to “PE and ROW only”—engineering and right-of-way work. The entry therefore establishes preparation for construction bidding, not full construction funding or an awarded construction contract.

Sources01
Reported from official public records. Our reporting method · Suggest a correction