Public records
SkyTrain plan would replace its entire fleet—and add four vehicles
A $27.4 million proposal would start manufacturing replacements for the 12 vehicles used since 2009, plus four more. Further modernization funding would still follow.

Current coverage updates this story. SkyTrain fleet overhaul wins a $27.4 million council vote →
Hartsfield-Jackson’s SkyTrain would replace its entire original fleet and grow by a third under a proposal heading to Atlanta City Council’s Transportation Committee on Nov. 9. Up to $27.4 million would begin manufacturing 12 replacement vehicles and four additional ones, for a 16-vehicle fleet.[1]
The manufacturing proposal we reported earlier is aimed at a fleet still made up of its original 12 vehicles, in service since 2009. The city’s resolution says numerous vehicles are nearing the end of their lives and need replacement.[1]
Resolution 26-R-4410 would fund Phase 3 of the airport’s 10-year SkyTrain modernization program with Crystal Mover Services. The proposed allocation is capped at $27,417,824. The resolution lists an initial $7.2 million budget and a $36.6 million supplement approved in June; adding this installment would bring those authorizations to about $71.2 million.[1]
That would not be the program’s final bill. The resolution says the aviation general manager will seek additional funding for later phases as the project proceeds.[1]
The money would start manufacturing, not put new vehicles into service immediately. The resolution gives no delivery or service-entry date, and the packet lists both committee and City Council consideration as pending—not approved.[1]
The Transportation Committee meeting is scheduled for 10 a.m. Nov. 9 at Atlanta City Hall, 55 Trinity Avenue. The packet also lists City Council consideration for Nov. 16 at 1 p.m. as pending.[1][2]
Sources
2 official sources cited in this report. The bracketed numbers in the text link here.
Reporting history
Newest first. Articles reflect what was known at publication.