Abbotts Bridge Road agreement would cover an estimated $2.43 million in water-main relocations

The proposed Fulton–GDOT agreement covers the Johns Creek corridor from Promise Parkway to Boles Road.

Current coverage updates this story. Abbotts Bridge water-main estimate rises 32% in new Fulton request →

Fulton County’s March 4, 2026, agenda requested approval of an agreement with the Georgia Department of Transportation for water-main relocations associated with widening and improvements to Abbotts Bridge Road in Johns Creek.⁠[1]

Item 26-0119 identifies the SR 120 corridor from Promise Parkway to Boles Road, under Project P.I. No. 721000. The estimated amount for the agreement’s utility work was $2,426,610. The entry is an approval request, not evidence that the agreement was authorized or construction began.⁠[1]

Sources

1 official source cited in this report. The bracketed numbers in the text link here.

Reporting history

Newest first. Articles reflect what was known at publication.

  1. Abbotts Bridge water-main estimate rises 32% in new Fulton request

    Published after this article

More from Fulton County

More in Fulton County →All stories →