Local brief
EV-charger redo approved: six ports first, four still conditional
The $407,941.40 contract puts North Dillon Town Park, the marina and Town Center first. Town Hall and Marina Park depend on rebates.
Dillon Town Council voted 7-0 on November 17 to approve a corrected $407,941.40 contract with Winn-Marion Barber, LLC, for Level 2 electric-vehicle chargers. The plan puts six ports at three sites in the first phase; another four ports at two sites remain contingent on Xcel Energy rebates.[1][2][3][4]
The $261,295.64 first phase has a specific priority order: North Dillon Town Park at 100C Tenderfoot Street, Dillon Marina at 150 Marina Drive, then Town Center at 124 Main Street.[4]
The optional $146,645.76 second phase covers Town Hall and the Marina Park restrooms. The agreement does not obligate Dillon to proceed with those sites: the town must authorize that phase in writing by March 1, 2027.[4]
The vote updates our pre-meeting report on the contract redo. Council had approved a $402,317 version on November 3, but staff says it found a hardware error November 9, before the contract was signed. The replacement adds $5,624.40 and specifies ABB chargers with displays, pedestals and built-in cable retraction.[1][2][4]
Rebates remain an important qualification. In its November 17 report, staff anticipated $169,190 in support—$99,190 from Xcel Energy and $70,000 from the Colorado Energy Office. Staff reported written confirmation of a state funding extension through the end of 2027. Xcel had indicated an extension through October 31, 2027, but formal reservation letters were still being worked out. The records reviewed do not establish whether those Xcel letters have since been finalized.[4]
The approved agreement sets October 31, 2027, as the completion deadline. It also requires a pre-construction meeting and written town instructions before work begins; approval alone is not a construction start.[4]
Nor is the contract price a settled all-in project cost. Staff says the town and Dillon Urban Renewal Authority have budgeted $500,000, with final site designs potentially bringing civil-construction costs or savings. The contractor’s proposal excludes utility-provider costs and utility-service upgrades beyond the connection to the provided transformer.[4]
Reported as of 9:47 a.m. MST November 18, 2026.[3]