Dillon’s EV-charger redo: three sites first, two tied to rebates
Staff seeks a corrected $407,941.40 contract. Town Hall and Marina Park chargers would be optional as officials work to formalize rebate extensions.
Current coverage updates this story. EV-charger redo approved: six ports first, four still conditional →
Dillon’s revised electric-vehicle charging plan would put six Level 2 charging ports at North Dillon Town Park, Dillon Marina and Town Center first. Another four—at Town Hall and near the Marina Park restrooms—would depend on Xcel Energy rebates.[1]
Town staff recommends a corrected $407,941.40 contract with Winn-Marion Barber, LLC, scheduled for Town Council consideration at 7 p.m. November 17. This account is reported as of 3:27 p.m. MST November 17, 2026, ahead of that meeting—not as a report of approval.[1]
Council approved the previous version 7-0 on November 3. Staff says it found a hardware error on November 9, before the contract was signed. The replacement quote is $5,624.40 higher and specifies ABB chargers with displays, pedestals and built-in cable retraction.[1]
The financing hinges in part on $169,190 in anticipated rebates: $99,190 from Xcel Energy and $70,000 from the Colorado Energy Office. Staff reports written confirmation that the state office will extend its funding through the end of 2027. Xcel has indicated an extension through October 31, 2027, but staff says formal reservation letters were still being worked out and the contract is needed to secure the extensions.[1]
The proposed contract would not obligate Dillon to build the second phase. The town would have until March 1, 2027, to authorize it in writing. The contract sets an October 31, 2027, completion deadline.[1]
There is substantial preparation left: the November 17 staff report says only one of the five locations was nearing completion of design and easement paperwork. The first-phase priority order is North Dillon Town Park at 100C Tenderfoot Street, Dillon Marina at 150 Marina Drive, then Town Center at 124 Main Street.[1]
The town and Dillon Urban Renewal Authority have budgeted $500,000, but the quoted contract is not a settled all-in project cost. Staff says final site designs could bring additional civil-construction costs or savings. The contractor’s proposal also excludes utility-provider costs and utility-service upgrades beyond the connection to the provided transformer.[1]
Sources
1 official source cited in this report. The bracketed numbers in the text link here.
Reporting history
Newest first. Articles reflect what was known at publication.
EV-charger redo approved: six ports first, four still conditional
Published after this article