New deck, old steel: the plan for Cochran Mill Park’s footbridge

The green-trail crossing would get new decking and railings. The city’s intended Dec. 3 award date is not a reopening promise.

The proposed fix for Cochran Mill Park’s green-trail footbridge would rebuild it from the steel beams up—not replace the entire structure. The city’s repair scope calls for retaining the existing steel I-beams and installing new pressure-treated framing, deck boards and welded-steel railings.⁠[1][2]

The documents add specifics to our earlier report on the safety closure, including which trail crossing is affected. Chattahoochee Hills, Georgia, set a Nov. 19 proposal deadline and lists Dec. 3 as its intended contract-award date. That is a procurement target, not an approval or a date visitors can expect to cross.⁠[1][2][3]

According to draft minutes of the Nov. 5 City Council meeting, Public Works/Parks Director Darold Wendlandt said 11 contractors attended that morning’s pre-bid meeting. He said the bridge was “shut down and cannot be walked on,” and that a contract award would come to council rather than be made by staff.⁠[3][4]

The work also involves an unresolved paint-handling question. In its written answers to bidders, the city says the existing steel coating has not been tested for lead. That leaves its lead content unknown; it does not establish that lead is present.⁠[2]

The scope requires plastic sheeting beneath the bridge to capture rust, paint and preparation debris. The city also says the contractor must demonstrate experience and qualifications in managing potentially hazardous coatings, containment, paint-debris disposal and measures to prevent environmental contamination.⁠[1][2]

The construction timetable needs care, too. Wendlandt told council he was allowing 60 days to complete the work. The written solicitation specifies an initial contract term of six months from the notice to proceed—a different measure from a construction estimate. Neither establishes a firm reopening date. The records reviewed do not establish a selected contractor, project price or whether the bridge has reopened since his Nov. 5 report.⁠[1][4]

Sources

4 official sources cited in this report. The bracketed numbers in the text link here.

Reporting history

Newest first. Articles reflect what was known at publication.

  1. Cochran Mill Park footbridge was closed for safety; bridge talks set Nov. 10