Royal 400 data center expansion would add Georgia Power substation
The September 3 Planning Commission agenda said staff had deferred the request and it would not be considered at that meeting.
The request concerns a 38.8-acre data center site at 4905 North Point Parkway.
What changes
The applicant asks to amend the Royal 400 Master Plan to allow utility substations through conditional-use approval, and also requests that approval for this site.