The supporting resolution reports $898,370.87 used from the RAISE grant. The closeout amendment has committee backing, not an executed agreement.
Explore the source documentsAtlanta’s Transportation Committee voted 4–0 Sept. 30 to recommend a grant-closeout amendment for the Stitch’s I-75/I-85 capping study. The supporting resolution says the study has been completed.
Sources01p. 102p. 1801p. 116The study concerns planning to cap the interstates in Downtown Atlanta and reconnect the street grid with pedestrian-oriented, multimodal streets. The supporting text reports $898,370.87 used from the RAISE grant and proposes a $2,036.41 funding reduction through the project-framework amendment. Study completion is not completion of the highway cap.
Sources01p. 11501p. 11602p. 18 Reported from official public records. Our reporting method · Suggest a correction