The $216,936 total is about 24% above the original authorization. The vote covers completed work, not another round of construction.
Atlanta City Council voted 13–0 on Nov. 16 to authorize a final $18,186 payment to the Georgia Department of Transportation for utility adjustments tied to Lindbergh Drive NE’s resurfacing.[1]
The reconciled utility bill totals $216,936—about 24% above the original $174,441.60 authorization. According to the resolution, Atlanta had already paid $198,750, leaving the $18,186 balance.[1]
Our earlier report covered the City Utilities Committee’s Nov. 10 recommendation. The full council has now adopted Resolution 26-R-4354 by consent vote, moving it beyond that committee stage.[1]
The authorization covers completed work, not a new construction project. The utility adjustments accompanied about 1.14 miles of milling and resurfacing from Piedmont Road NE to the DeKalb County line in Fulton County. Construction began in October 2023, and final construction reconciliation was completed in January 2026, the resolution says.[1]
The finished work differed from the initial engineering assessment: crews adjusted 27 manholes and 18 water valves to road grade, rather than the anticipated 14 manholes and 37 valves. The resolution lists those changes but does not explain how they affected the final price.[1]
The packet establishes council adoption, but does not confirm that the final payment has been sent.[1]