Campbellton Road's $824,096 pedestrian-improvement contract proposal remains held

The proposal covers 0.9 miles of roadway and pedestrian work. Its completion periods would begin with a notice to proceed, not the committee meeting.

Explore the source documents

A proposed $824,096 contract for 0.9 miles of roadway and pedestrian improvements along Campbellton Road SW remained held in Atlanta’s Transportation Committee on Sept. 30. Resolution 26-R-3253 would authorize an agreement with SD&C, Inc.; the supporting text identifies the company as the lowest responsible and responsive bidder.

Sources01p. 1901p. 12501p. 1

The proposed contract would allow 280 calendar days for substantial completion and 340 days for final completion, measured from issuance of a notice to proceed. The minutes list Oct. 5 at 1 p.m. as the next checkpoint. The hold is not a construction authorization, and the proposed agreement requires legal review, execution, attestation and delivery before binding the city.

Sources01p. 1901p. 126