Adamsville Pump Station upgrade seeks nearly three more years for completion

A time-only change would move final completion to June 2029 without raising the $29.3 million contract amount.

Current coverage updates this story. Atlanta panel to consider 2029 deadline for Adamsville water-pump upgrades →

An ordinance listed for first reading on the City Utilities Committee’s Sept. 29 agenda proposes extending the Adamsville Pump Station upgrade contract by 958 days. Final completion would move from Nov. 7, 2026, to June 22, 2029; the agenda listing does not approve the change order.⁠[1]

The ordinance attributes the delay to pump-sizing and electrical-voltage decisions that slowed procurement and longer lead times for critical equipment, including a generator. The proposed extension with Ruby-Collins/Benchmark Joint Venture would not change the $29,318,282 contract amount. The change order would require further steps before becoming binding.⁠[1]

Sources

1 official source cited in this report. The bracketed numbers in the text link here.

Reporting history

Newest first. Articles reflect what was known at publication.

  1. Council OKs 958 extra days for Adamsville pump upgrades, not more contract money

    Published after this article
  2. Atlanta panel to consider 2029 deadline for Adamsville water-pump upgrades

    Published after this article

More from Atlanta

More in Atlanta →All stories →