Adamsville pump-station proposal would move completion from November 2026 to June 2029

The proposed change adds 958 calendar days at no additional city cost. Utilities Committee consideration is listed for Oct. 13.

Explore the source documents

A proposed change order for Atlanta's Adamsville Pump Station upgrades would move the final contract completion date from Nov. 7, 2026, to June 22, 2029. Ordinance 26-O-1553 specifies a 958-calendar-day extension at no additional cost to the city.

Sources01p. 50

The proposal concerns the Watershed Management agreement with Ruby-Collins/Benchmark, LLC Joint Venture. Draft action minutes record a 12–0 referral to the City Utilities Committee Oct. 5 and list Oct. 13 at 10 a.m. as the next checkpoint. The referral does not approve the revised completion date, and the minutes do not explain the reason for the extension.

Sources01p. 101p. 50