North Fulton wastewater operations extension proposed at up to $12.47 million in March
The Veolia request covered a maximum 183-day extension from April 1 through September 30, 2026.
Fulton County’s March 18, 2026, agenda requested up to $12,470,486.61 to extend Veolia Water North America-South, LLC’s contract for wastewater facilities and pump stations in the North Fulton service area.[1]
Item 26-0168, under contract 19RFP090419K-DB, proposed an additional maximum 183 days from April 1 through September 30, 2026, to support uninterrupted water and wastewater operations and maintenance. The agenda establishes the extension request, not that it was authorized or performed.[1]