Why Frisco plans to split up the Creekside and Emily Lane pipe repairs

Phasing the water-main replacement will add mobilization costs, staff say, but limit disruption. Design is planned for 2027.

Splitting the Creekside and Emily Lane water-main replacement into phases will add the cost of bringing crews back. Frisco staff say the alternative—doing the work in one section—would mean greater disruption and outages.⁠[1]

That was the trade-off staff laid out at the Colorado town’s Oct. 27 water-system work session. Since our earlier repair-plan preview, council has adopted the town’s 2027 budget and 2027–2031 capital program through Resolution 26-24.⁠[1][2][3][4][5][6][7]

Public Works’ project sheet says groundwater is deteriorating the Creekside/Emily Lane mains. The Water Fund schedule lists $120,000 for design in 2027, followed by $600,000 construction phases in each of 2028 and 2029. North Fifth, Sixth and Seventh avenue replacements follow: design in 2029 and construction in 2030 and 2031.⁠[8]

The presentation offered a blunt illustration of the problem elsewhere in the system: photos of corroded pipes from the Lagoon water-main replacement. Staff described “thumb-sized holes” through which water was escaping.⁠[9][10]

Staff said Lagoon’s replacement uses ductile iron with cathodic protection intended to reduce corrosion and extend pipe life, and that Hawn Drive would likely receive the same treatment. Asked about Creekside and Emily Lane, staff cautioned that the project had not yet been designed and declined to get ahead of the engineer.⁠[8][11][12][13][14][15]

Timing brings another trade-off. Staff intend to target main replacements later in the fall, when lower groundwater levels reduce the expense of removing water from excavations. They said Lagoon had needed little of that dewatering—but keeping lines from freezing also brings costs.⁠[16][17]

The treatment plant has a separate repair need: roof fractures and water leaking into the rear walls. Its project sheet calls for design in 2027 and rehabilitation in 2028.⁠[8]

The cost conflict flagged in our preview is narrower, but not resolved. The packet’s presentation priced Creekside/Emily Lane design and construction at a combined $3.525 million. The live slide instead used the Water Fund schedule’s $1.32 million figures, yet still displayed an $11.7 million program total and annual totals that exceed its listed projects. The Water Fund schedule totals $7.855 million across a different mix of projects. Those records do not establish a reconciled overall price or an approved cost reduction.⁠[8][18]

Adopting the capital program is not the same as approving every construction contract. The work-session report says implementation depends on annual appropriations, available Water Fund resources and funding agreements, with future contracts and budget adjustments subject to their own approval process.⁠[8]

Reported as of Oct. 28, 2026.⁠[2]

Sources

19 official sources cited in this report. The bracketed numbers in the text link here.

Reporting history

Newest first. Articles reflect what was known at publication.

  1. Groundwater is damaging mains. Frisco’s proposed repairs stretch to 2031.