Construction-water charge could rise eightfold as filling station carries into 2027
The proposed schedule lists $40 per 1,000 gallons, up from $5. Shipping lead times have pushed station work into next year, with a May 15 operating target.
Contractors buying construction water from Frisco, Colorado, would pay $40 per 1,000 gallons under the proposed 2027 fee schedule—eight times the listed 2026 charge of $5.[1][2]
That jump is specific to construction water, not an eightfold increase across all water charges. The same table leaves the water base rate at $57 and the construction-water connection fee at $100.[1]
The figures appear in the packet for the Town Council’s Oct. 27 consideration of the 2027 budget and five-year capital program. A proposed budget resolution provides for final public comment that day. The packet is not evidence that the charge or project funding has been adopted.[1][2]
Meanwhile, shipping lead times have carried work on the town’s bulk-water filling station into 2027. The station project sheet says work began in 2026 and targets full operation by May 15, 2027. It requests $40,000 for next year and lists $150,000 in total funding.[1]
The station is intended to let contractors fill construction-water tanks and improve circulation in the town’s water distribution system. But the sheet gives conflicting location information: its description says “at the Marina,” while its location field says “Public Works.” It does not resolve which site contractors should use.[1]
Reported as of Oct. 26, 2026.[2]