A $950,000 plan targets Highway 9’s pedestrian gap near Walmart

The budget proposal would put $100,000 toward design in 2027. Construction would follow Exit 203 work, but the packet gives conflicting years.

A missing stretch of pedestrian path along southbound Highway 9 could get design money in 2027 under a $950,000 proposal heading to Frisco, Colorado’s Town Council on Oct. 27.⁠[1][2]

The town’s project sheet locates the gap between School Road and the Walmart entrance. The aim is to connect the town core along Highway 9 to trailheads north of Interstate 70. Town construction would follow CDOT’s Exit 203 improvements, according to the proposal.⁠[1]

The proposed five-year funding schedule puts $100,000 in 2027 and $850,000 in 2030. Staff’s narrative calls for design in 2027—so next year’s allocation would be a planning step, not a promised opening.⁠[1]

The construction year is less clear. The narrative anticipates building the Lusher Gap connection in 2029, while both the project’s funding schedule and the capital-program summary place the larger allocation in 2030. The packet leaves that discrepancy unresolved.⁠[1]

Grant help is prospective in the proposal: staff say they plan to apply during CDOT’s next TAP grant cycle to offset design and construction costs. That is an application plan, not evidence of an award.⁠[1]

Council is scheduled to consider Resolution 26-24, which would adopt the 2027 budget and 2027–2031 capital program, during its Oct. 27 regular meeting beginning at 7 p.m. at Town Hall, 1 Main St. The draft resolution says final budget comments will be accepted at that night’s public hearing.⁠[1][2]

Reported as of Oct. 26, 2026.⁠[2]