A $2 million Island Grill–Lund House redo would wait until late 2030

The proposed capital plan splits funding between 2030 and 2031. A separate Lund House restroom expansion has $700,000 requested for 2027.

A proposed $2 million remodel of the Island Grill and Lund House at Frisco Bay Marina comes with a long lead time: work would begin in late 2030 and finish before the marina opens for the 2031 boating season.⁠[1]

Frisco’s proposed 2027–2031 capital program lists $1 million for the project in 2030 and another $1 million in 2031, with nothing requested for 2027 through 2029. The listed funding sources are real estate investment fees and General Fund transfers.⁠[1]

The town’s project description calls for analyzing and making changes to improve service at the Island Grill, along with remodeling the Lund House to better accommodate staff and visitors. This is a proposed capital allocation, not a construction award.⁠[1][2]

The long-range remodel is separate from a nearer-term restroom expansion attached to the Lund House. That project requests $700,000 for 2027 to renovate and expand the existing facilities, including an additional restroom. Its project sheet lists a 2026 start and estimated completion in 2027; the $700,000 is the 2027 request, while the sheet lists $1.4 million in total funding.⁠[1]

Frisco’s Town Council in Colorado is scheduled to consider the five-year capital program alongside the 2027 budget on Oct. 27 under Resolution 26-24. The proposed resolution identifies that date as the public hearing for final budget comments. The regular meeting starts at 7 p.m. at Town Hall, 1 Main Street.⁠[1][2]

Reported as of Oct. 26, 2026.⁠[2]

Sources

2 official sources cited in this report. The bracketed numbers in the text link here.

Nearby reporting

Nearby reports may concern separate cases.

More from Frisco

More in Frisco →All stories →