North Fork’s $20.32 million request wins committee backing
A previously held $17.47 million funding measure advanced with the contract changes. The package still needs final city authorization.
Atlanta’s City Utilities Committee unanimously recommended $20.32 million in additional contract funding for the North Fork storage tank and pump station on Nov. 24, moving the package closer to—but not granting—final city authorization.[1]
The package we previously explained now has favorable recommendations on all four measures: two contract increases and two matching budget transfers. That includes the $17.47 million reserve-transfer ordinance, 26-O-1530, which the minutes note was held Sept. 29 at the department’s request. The draft minutes list Dec. 7 at 1 p.m. as the next action date.[1]
The larger contract change would add up to $17,469,027 for construction contractor Ruby-Collins. The watershed department’s explanation ties the request to an approximately two-year delay involving the Georgia Department of Transportation lease, with the construction notice to proceed issued Feb. 5, 2024. It cites nearly 14,000 contractor labor hours spent reviewing constructability and resolving issues before construction, along with higher material and subcontract costs and permitting fees.[1][2]
Benchmark Barge Design Solutions would receive up to $2,851,870 more under the other contract measure. It would extend the agreement through Dec. 31, 2027, retroactively effective Sept. 7, 2023, and ratify services provided and outstanding invoices. Both contract measures also seek waivers of the city’s procurement source-selection provisions.[1]
The two budget ordinances would move matching amounts into North Fork: $17,469,027 from commercial-paper fund reserves and $2,851,870 from completed-project balances and reserves in the Water and Wastewater Renewal and Extension Fund. Those transfers and the contract increases are funding and spending-authority measures for the same package—not separate costs to add together.[1]
The project is under construction on GDOT property near Sidney Marcus Boulevard and Buford Highway. Plans call for a 15-million-gallon tank and a pump station rated at 75 million gallons a day to capture excess wastewater during major storms and reduce sanitary sewer overflows. Cheshire Farm Trail improvements are also part of the project. The construction ordinance describes Ruby-Collins as actively building it; the earlier funding hold did not establish a work stoppage.[1][2]