Atlanta zoning board urges denial of 2,250-space airport lot on Cleveland Avenue
Planners say the round-the-clock Fast Park & Relax proposal conflicts with investments meant to make the corridor more walkable, bikeable and transit-friendly.
Explore the source documents
Atlanta’s Zoning Review Board has joined city planners and Neighborhood Planning Unit Z in recommending denial of a 2,250-space airport-parking facility on Cleveland Avenue SW. The board’s Oct. 8 recommendation is not a final City Council rejection of the special-use permit.
Sources01p. 402p. 27Chavez Properties Acquisitions, LLC proposes operating the 21.28-acre facility as Fast Park & Relax, with parking and shuttles for passengers using Hartsfield-Jackson’s domestic terminal. It would run around the clock, every day of the year. The requested permit would have no fixed end date.
Sources02p. 2601p. 402p. 27The staff report describes a corridor being improved for a different way of getting around. It cites $5 million in Atlanta Department of Transportation capital projects underway and a broader MARTA project costing $15 million–$20 million, intended to make the area more walkable, bikeable and transit-friendly. A proposed rapid-transit stop at Old Hapeville Road would connect through East Point station to the airport.
Sources02p. 2602p. 28The parking operation would put clients, employees and emergency vehicles through one driveway on Cleveland Avenue. Although the applicant supplied a traffic study, planners say the submitted documents included no recommended pedestrian improvements or cycling analysis.
Sources02p. 2502p. 27More from Atlanta