Adamsville pump-station proposal would move completion from November 2026 to June 2029
The proposed 958-day extension would add no cost to an upgrade contract originally capped at $29.32 million.

Current coverage updates this story. Atlanta panel to consider 2029 deadline for Adamsville water-pump upgrades →
An Atlanta ordinance proposes extending the Adamsville Pump Station Upgrades contract by 958 calendar days, moving final completion from Nov. 7, 2026, to June 22, 2029, at no additional cost to the city.[1]
The supporting ordinance says decisions affecting pump sizing and electrical voltage delayed procurement, while supply-chain lead times for critical equipment, including the generator, increased substantially. The requested extension would not change the scope of work.[1]
Ordinance 26-O-1553 would authorize a change order with Ruby-Collins/Benchmark, LLC Joint Venture for Watershed Management. The original contract ceiling is $29,318,282. This is a proposed extension, not an executed change order; the text requires legal approval, execution, attestation and delivery before it binds the city.[1]
Sources
2 official sources cited in this report. The bracketed numbers in the text link here.
Reporting history
Newest first. Articles reflect what was known at publication.
Council OKs 958 extra days for Adamsville pump upgrades, not more contract money
Published after this articleAtlanta panel to consider 2029 deadline for Adamsville water-pump upgrades
Published after this article