Local brief
16 committee holds for Campbellton Road’s $824,096 pedestrian contract proposal
The work would cover 0.9 miles. The city’s legislative record lists Dec. 7 as the next council date, but doesn’t say whether the contract will come up for a vote.
Atlanta’s Transportation Committee kept the proposed Campbellton Road contract on hold Nov. 23, according to its draft minutes. The legislative record lists the resolution as pending for the Dec. 7 City Council meeting at 1 p.m. That’s the next date on the record, not a scheduled vote on the contract.[1]
The committee first held Resolution 26-R-3253 on Feb. 25 for further review and more information. The legislative history records 16 committee holds through Nov. 23, not counting the times the full council returned the measure as held. The Nov. 23 minutes give no reason for the latest hold.[1]
The proposal covers 0.9 miles of road and pedestrian improvements along Campbellton Road SW. The resolution identifies SD&C Inc. as the lowest bidder to meet the city’s requirements. Of the proposed $824,096 contract cap, about $817,794 would come from an intergovernmental grant fund and about $6,302 from a water and wastewater bond fund.[1]
Under the proposed terms, SD&C would have 280 calendar days to substantially complete the work and 340 to finish it. Both deadlines would run from a notice to proceed. The resolution does not set a date for that notice.[1]