Royal 400 data center substation request deferred by staff

The proposal pairs a Georgia Power substation with expansion of the existing data center at 4905 North Point Parkway.

Explore the source documents

A newer report updates this story. Royal 400 substation proposal heads to October hearings →

The September 3 agenda said the request would not be considered at that Planning Commission meeting.

The details

The proposal concerns a 38.8-acre site in the Royal 400 Master Plan. The applicant seeks to add utility substations as a conditional use under that plan and obtain permission for a substation on the property.

Reported from official public records. Our reporting method · Suggest a correction

More from Alpharetta

Reporting history

Newest first. Articles reflect what was known at publication.

  1. Staff backs Royal 400 substation with buffer, screening and noise-study conditions

    Published after this article
  2. Royal 400 substation proposal heads to October hearings

    Published after this article

More in Alpharetta →All stories →