Royal 400 Data Center named in Alpharetta planning recommendation
The Composite Planning Case identifies Royal 400 Data Center as the subject of a planning recommendation.
Current coverage updates this story. Planners back Royal 400’s substation—and add a 12-foot sculpture →
The public record gives readers a specific project name and case number to track: MP-26-13.
Sources
1 official source cited in this report.
Reporting history
Newest first. Articles reflect what was known at publication.
Planners back Royal 400’s substation—and add a 12-foot sculpture
Published after this articleStaff backs Royal 400 substation with buffer, screening and noise-study conditions
Published after this articleRoyal 400 substation proposal heads to October hearings
Published after this article
Case summary
This retained record is not automatically updated. Check the linked official sources and related reporting for later developments.
A proposal or recommendation does not establish approval.
- Road or project area
- Land Lots 850, 851, 858 & 859, 1st District, 2nd Section, Fulton County, GeorgiaSource · page 1 ↗ · Find on map ↗
- Project site
- 4905 North Point ParkwaySource ↗ · Find on map ↗
- Site area (acres)
- 38.8Source · page 1 ↗
- What the record describes
- Consideration of a request for master plan amendment and conditional use to allow a Georgia Power substation in conjunction with an expansion of an existing data center on 38.8 acres in the Royal 400 Master Plan.Source · page 1 ↗
- Project named in the record
- Royal 400 Data CenterSource ↗
- What is proposed
- Utility SubstationSource · page 1 ↗
Some details have no verified date. Their source links remain available.
Final-decision evidence is incomplete. The timeline may contain individual actions or recommendations. Check the official record for the complete decision and any later action.